Project overview – The project comprised of the demolition of Toy World and the shop units below at Regents Arcade, Cheltenham.
Scope of Work – Strip out works were carried out over the 3 floors being demolished. All suspended and plasterboard ceilings, wall coverings and floor coverings were removed using hand tools and safely disposed of.
The ground floor (shop units & cellar below), first floor (Toy World) and second floor (mezzanine level of the first floor) was demolished using a 30 tonne 360 excavator.
All waste materials were removed from the site and taken to Smiths Waste Management Facility at Moreton Valence.
The site was left in a tidy and safe condition.